SOFTROBOT AI ERP - ATP PROJECT ITEM DELIVERY SCHEDULER

ATP INPUT SOURCES

AI ATP ENGINE

AUTO GENERATED TICKETS

EPC / HVAC PROJECT ATP SCHEDULER

BBU Project Item Department Customer Required Date Engineering Status Material ATP Procurement ETA Production Days Inspection Days Dispatch Days Total Lead Time ATP Delivery Date Delay Days Status ERP Action Formula Logic
BBU-001 AHU 15000 CFM HVAC Engineering 25-May-2026 Approved Available - 7 2 2 11 20-May-2026 0 ON TIME Release Production WO Prod + Insp + Dispatch
BBU-002 Chilled Water Pipe Procurement 18-May-2026 Approved Partial 15-May-2026 4 1 1 10 21-May-2026 3 RISK Expedite Vendor PO ETA + Production LT
BBU-003 Ducting Package Production 30-May-2026 Approved Available - 15 2 3 20 28-May-2026 0 ON TRACK Continue Production Current Date + Balance LT
BBU-004 Cooling Tower Vendor Supply 22-May-2026 Approved Not Available 28-May-2026 0 1 2 11 31-May-2026 9 DELAY Escalate To SCM Head Vendor ETA + Dispatch LT
BBU-005 Electrical Panel Electrical 12-Jun-2026 Drawing Pending Available - 8 2 1 14 18-Jun-2026 6 ENGG HOLD Generate Design Escalation Drawing Delay + MFG LT
BBU-006 Fire Dampers QA/QC 28-May-2026 Approved Available - 6 5 2 13 29-May-2026 1 QC RISK Prioritize Inspection Production + QC + Dispatch

ATP DELIVERY CALCULATION LOGIC

Logic Formula Purpose
ATP Quantity Stock + Incoming Supply - Allocated Qty Available quantity for customer promise
Delivery Date Material ETA + Production LT + QC LT + Dispatch LT Customer committed delivery date
Delay Days ATP Date - Customer Required Date Delay measurement
Critical Path MAX(Engineering, Procurement, Production) Identify bottleneck
Project Completion % Completed BBU / Total BBU Project tracking
Material Constraint IF(Material ATP = 0) Generate SCM escalation

DEPARTMENT-WISE EPC / HVAC FLOW

Department ERP Responsibility ATP Impact
Engineering Drawings / BOM Release Cannot start procurement without approval
SCM Procurement PO / Vendor Follow-up Controls material availability
Stores Inventory Reservation ATP stock allocation
Production Manufacturing Determines fabrication completion
QA/QC Inspection / Testing Shipment clearance
Projects Site Coordination Delivery sequencing
Logistics Dispatch Planning Transit scheduling
CRM Customer Promise Management Customer communication

AI GENERATED ERP TICKETS

Trigger AI Ticket Department
Engineering Drawing Pending Urgent Design Approval Engineering
Material Shortage Immediate Procurement SCM
Vendor Delay Vendor Escalation Purchase
Production Overload Capacity Balancing Production
Inspection Delay QA Priority Inspection QA/QC
Dispatch Risk Transport Planning Alert Logistics
Customer Delivery Delay CRM Customer Intimation CRM