Pre-Tender Status
Market Research Completed
Active Tenders
5 Tenders (₹25 Cr Value)
Post-Tender Projects
12 Projects (85% On-time Delivery)
| Tender ID | Estimated Cost | Bid Value | Margin % | Competitor Benchmark | Bid Status |
|---|---|---|---|---|---|
| T-2023-045 | ₹4.8 Cr | ₹5.2 Cr | 8.3% | ₹5.0 Cr (Competitor A) | Under Evaluation |
Material Cost Variance
+12%
Steel Price Increase
Labor Efficiency
-8%
Against Estimate
| Work Package | Planned Cost | Actual Cost | Variance | CPI |
|---|---|---|---|---|
| Structural Works | ₹1.2 Cr | ₹1.35 Cr | +12.5% | 0.89 |
| Deliverable | Target Margin | Actual Margin | Cost Variance | ROI |
|---|---|---|---|---|
| Electrical Works | 15% | 17.2% | -8% | 1.24 |
High Risk Items
Mitigation Strategies
| Evaluation Criteria | Weightage | Our Score | Competitor Avg. | Gap Analysis |
|---|---|---|---|---|
| Technical Compliance | 40% | 92% | 85% | +7% |
Cost Optimization
Risk Mitigation
* Update tender metrics daily and review with project team every Wednesday AM.